* Supervise, actively participate, and contribute to all committees, tasks, and activities as per the Grant Agreement and Executive Board decisions. | * Supervise, actively participate, and contribute to all committees, tasks, and activities as per the Grant Agreement and Executive Board decisions. | ||
− | == Budget Allocation Conditions == | + | === Budget Allocation Conditions === |
* Adhere to guidelines, tasks, and activities described in the GA and additional guidelines by the Executive Board. | * Adhere to guidelines, tasks, and activities described in the GA and additional guidelines by the Executive Board. | ||
* The employing Associated Partner from Switzerland takes the lead for work packages 3 and 7 without additional budget allocation. | * The employing Associated Partner from Switzerland takes the lead for work packages 3 and 7 without additional budget allocation. | ||
* Coordinator does not receive additional budget allocation for leading work packages 6 (doctoral training) and 8 (project management). | * Coordinator does not receive additional budget allocation for leading work packages 6 (doctoral training) and 8 (project management). | ||
− | == Changes and Non-Fulfillment == | + | === Changes and Non-Fulfillment === |
* In case of changes in IRP allocations, WP leaders, or beneficiaries, budget allocation will be adjusted. | * In case of changes in IRP allocations, WP leaders, or beneficiaries, budget allocation will be adjusted. | ||
* If a beneficiary does not fulfill obligations, the Coordinator may propose transferring tasks and budget to another beneficiary with General Assembly approval. | * If a beneficiary does not fulfill obligations, the Coordinator may propose transferring tasks and budget to another beneficiary with General Assembly approval. |
Revision as of 18:08, 22 January 2024
Work Package Leads
As a WP lead, a monthly report needs to be written. The template for this report is given. Please download the file as a word document. After it has been filled in, store it in the drive given below as followes: [WPnumber]_[Mnumber].
The template is the following document: https://docs.google.com/document/d/1WfpG8hWBLzcPww3SkuLFxu5KiQb3JSQ8/edit.
It should be stored in the following folder: https://drive.google.com/drive/u/1/folders/1eCNLR84ZvLbv26MB7VIS6wfEX8GogUCa.
Work Package Leads requirements
The monthly reporting should satisfy predetermined requirements. These requirements are summarised below, but the full document is shown in the following presentation: https://docs.google.com/presentation/d/1l52nD9v7Nc5b4hA4EVwPF9ss55AJNxGx/edit#slide=id.p1
Requirements Summary
1. Project Coordination
- Assign a designated project coordination team.
- Fulfill all related tasks and activities.
2. Consortium Wide Tool
- Provide relevant material in the consortium-wide tool at least eight weeks before the scheduled event (latest by M24).
- Content and amount of material for PhD-level courses and ECTS must be approved by the Executive Board.
- Adhere to guidelines for doctoral training.
- Submit evaluation reports within four weeks of the event.
- Budget allocation is proportional to the number of ECTS taught.
3. Work Package Requirements
- Achieve deliverables and milestones related to the respective IRPs of the work package.
- Submit a detailed work package plan within three months of the project start.
- Update the plan every six months and get approval from the Executive Board.
- Appoint a co-WP lead from another country within three months.
- Organize one WP research conference by M42.
- Provide monthly WP update reports.
- Convene quarterly meetings.
- Perform all tasks and activities within given time frames.
- Budget allocation is proportional to fellow person-months involved.
4. Fellow Participation
- Fellow must participate in at least 30 ECs of training and networking activities.
- Achieve deliverables and milestones related to the respective IRP.
- Adhere to guidelines for doctoral training, dissemination, exploitation, and communication.
5. IRP of a Fellow
- Achieve deliverables and milestones related to the IRP.
- Supervise, actively participate, and contribute to all committees, tasks, and activities as per the Grant Agreement and Executive Board decisions.
Budget Allocation Conditions
- Adhere to guidelines, tasks, and activities described in the GA and additional guidelines by the Executive Board.
- The employing Associated Partner from Switzerland takes the lead for work packages 3 and 7 without additional budget allocation.
- Coordinator does not receive additional budget allocation for leading work packages 6 (doctoral training) and 8 (project management).
Changes and Non-Fulfillment
- In case of changes in IRP allocations, WP leaders, or beneficiaries, budget allocation will be adjusted.
- If a beneficiary does not fulfill obligations, the Coordinator may propose transferring tasks and budget to another beneficiary with General Assembly approval.